Conceptual Design of Gas Transfer Pipeline
Client: National Petroleum Company| Country: Jordan| Period: 2001
Scope of work:
Consulting services for a detailed conceptual design of an approximately 60 km gas transfer pipeline to connect natural gas wells in the southern part of the Risha field to the processing plant at the north sector of the field.
The conceptual design was performed with the use of the TGNET Simulation Program, identifying the optimum pipe size and taking into consideration that no compressor stations were to be use. The ASME guide was used and the relevant pipe specifications (pipe wall thickness, material, insulation, etc.) were provided.